Substation Scout

Mays Landing 12kV

PJM queue ID W1-092 Terminal status

Queue IDW1-092
Project nameMays Landing 12kV
Status (as published)Withdrawn
SubstationMays Landing
Point of interconnectionMays Landing 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity3.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-07-21
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8.7
Mw Capacity3.3
Mfo8.7
Withdrawn Date1/13/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.