Central Solar Park

PJM queue ID W1-036 Terminal status

Queue IDW1-036
Project nameCentral Solar Park
Status (as published)Withdrawn
SubstationMatt Funk-Tech Drive
Point of interconnectionMatt Funk-Tech Drive 138kV
CountyRoanoke
StateVA
Voltage138 kV
Capacity5.9 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2012-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy45
Mw Capacity5.85
Mfo45
Withdrawn Date3/21/2012