Fairfield Renewable Energy Facility

PJM queue ID W1-033 Terminal status

Queue IDW1-033
Project nameFairfield Renewable Energy Facility
Status (as published)Withdrawn
SubstationPumphrey
Point of interconnectionPumphrey 115kV
CountyBaltimore City
StateMD
Voltage115 kV
Capacity25 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2016-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy25
Mw Capacity25
Mfo157
Withdrawn Date5/11/2016