Substation Scout

Fairton 69kV III

PJM queue ID W1-023 Terminal status

Queue IDW1-023
Project nameFairton 69kV III
Status (as published)Withdrawn
SubstationFairton III
Point of interconnectionFairton 69kV III
CountyCumberland
StateNJ
Voltage69 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-07-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity3.8
Mfo10
Withdrawn Date2/18/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.