Woodruffs Gap 345kV

PJM queue ID V4-017 Terminal status

Queue IDV4-017
Project nameWoodruffs Gap 345kV
Status (as published)Withdrawn
SubstationWoodruffs Gap
Point of interconnectionWoodruffs Gap 345kV
CountySussex
StateNJ
Voltage345 kV
Capacity1.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2010-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3.5
Mw Capacity1.3
Mfo3.5
Withdrawn Date2/15/2012