Substation Scout

Churchmans

PJM queue ID V4-003 Terminal status

Queue IDV4-003
Project nameChurchmans
Status (as published)Withdrawn
SubstationChurchmans
Point of interconnectionChurchmans
CountyNew Castle
StateDE
VoltageNot reported
Capacity5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2010-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy14
Mw Capacity5
Mfo14
Withdrawn Date5/17/2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.