PJM queue ID V3-062 Terminal status

Queue IDV3-062
Project nameMcConnellsburg-Guilford 138kV
Status (as published)Withdrawn
SubstationMcConnellsburg-Guilford
Point of interconnectionMcConnellsburg-Guilford 138kV
CountyFranklin
StatePA
Voltage138 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date11/27/2012