Substation Scout

Morris 34.5kV

PJM queue ID V3-005 Terminal status

Queue IDV3-005
Project nameMorris 34.5kV
Status (as published)Withdrawn
SubstationMorris
Point of interconnectionMorris 34.5kV
CountyMorris
StateNJ
Voltage34.5 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity3.8
Mfo10
Withdrawn Date11/7/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.