Substation Scout

Galion-Muskingham River 345kV

PJM queue ID V2-023 Terminal status

Queue IDV2-023
Project nameGalion-Muskingham River 345kV
Status (as published)Withdrawn
SubstationGalion-Muskingham River
Point of interconnectionGalion-Muskingham River 345kV
CountyMorrow
StateOH
Voltage345 kV
Capacity37.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2012-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy250.5
Mw Capacity37.5
Mfo250.5
Withdrawn Date4/7/2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.