Seneca Wind

PJM queue ID U4-028 Terminal status

Queue IDU4-028
Project nameSeneca Wind
Status (as published)Withdrawn
SubstationFostoria Central-Greenlawn-Howard
Point of interconnectionFostoria Central-Greenlawn-Howard 138kV
CountySeneca
StateOH
Voltage138 kV
Capacity13 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2020-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity13
Mfo100
Withdrawn Date11/5/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.