Mendota 138kV

PJM queue ID U4-006 Terminal status

Queue IDU4-006
Project nameMendota 138kV
Status (as published)Withdrawn
SubstationMendota
Point of interconnectionMendota 138kV
CountyLasalle
StateIL
Voltage138 kV
Capacity20 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2012-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date9/5/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.