PJM queue ID U3-005 Terminal status

Queue IDU3-005
Project nameMeadow Brook
Status (as published)Withdrawn
SubstationMeadow Brook
Point of interconnectionMeadow Brook
CountyUnknown
StateVA
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2008-12-31
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo0
Withdrawn Date2/1/2012