Dickerson 230kV

PJM queue ID U2-082 Terminal status

Queue IDU2-082
Project nameDickerson 230kV
Status (as published)Withdrawn
SubstationDickerson
Point of interconnectionDickerson 230kV
CountyMontgomery
StateMD
Voltage230 kV
Capacity400 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2012-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy400
Mw Capacity400
Mfo400
Withdrawn Date12/1/2008

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.