Susquehanna-Roseland 500kV

PJM queue ID U2-075 Terminal status

Queue IDU2-075
Project nameSusquehanna-Roseland 500kV
Status (as published)Withdrawn
SubstationSusquehanna-Roseland
Point of interconnectionSusquehanna-Roseland 500kV
CountyLackawanna
StatePA
Voltage500 kV
Capacity636 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2012-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy636
Mw Capacity636
Mfo636
Withdrawn Date4/13/2009