Substation Scout

Cedar 230kV

PJM queue ID T81 Terminal status

Queue IDT81
Project nameCedar 230kV
Status (as published)Withdrawn
SubstationCedar
Point of interconnectionCedar 230kV
CountyOcean
StateNJ
Voltage230 kV
Capacity70 MW
Resource (as published)Offshore Wind
Resource categoryOffshore Wind (normalised for filtering)
Target commercial operation2012-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy350
Mw Capacity70
Mfo350
Withdrawn Date7/18/2008

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.