Substation Scout

Four Rivers 500kV

PJM queue ID T168 Terminal status

Queue IDT168
Project nameFour Rivers 500kV
Status (as published)Withdrawn
SubstationFour Rivers
Point of interconnectionFour Rivers 500kV
CountyHanover
StateVA
Voltage500 kV
Capacity1,010 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2013-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1010
Mw Capacity1010
Mfo1010
Withdrawn Date7/21/2009

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.