Substation Scout

AP South 500kV

PJM queue ID T145 Terminal status

Queue IDT145
Project nameAP South 500kV
Status (as published)Withdrawn
SubstationAP South
Point of interconnectionAP South 500kV
CountyNot reported
StateNot reported
Voltage500 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2008-12-31
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo0
Withdrawn Date12/29/2009

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.