Substation Scout

Pocomoke

PJM queue ID T144 Terminal status

Queue IDT144
Project namePocomoke
Status (as published)Withdrawn
SubstationPocomoke
Point of interconnectionPocomoke
CountySomerset
StateMD
VoltageNot reported
Capacity10 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2010-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity10
Mfo19.8
Withdrawn Date7/30/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.