Substation Scout

Powell Generation Facility

PJM queue ID T134 Terminal status

Queue IDT134
Project namePowell Generation Facility
Status (as published)Withdrawn
SubstationChalk Point-Bowie
Point of interconnectionChalk Point-Bowie 230kV
CountyPrince George's
StateMD
Voltage230 kV
Capacity325 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2018-07-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy325
Mw Capacity325
Mfo325
Withdrawn Date9/25/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.