Substation Scout

Powell Generation Facility

PJM queue ID T133 Terminal status

Queue IDT133
Project namePowell Generation Facility
Status (as published)Withdrawn
SubstationChalk Point-Bowie
Point of interconnectionChalk Point-Bowie 230kV
CountyPrince George's
StateMD
Voltage230 kV
Capacity225 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2018-07-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy225
Mw Capacity225
Mfo225
Withdrawn Date9/25/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.