Substation Scout

Potter Wind Farm

PJM queue ID T121 Terminal status

Queue IDT121
Project namePotter Wind Farm
Status (as published)Withdrawn
SubstationPotter-Gold
Point of interconnectionPotter-Gold 115kV
CountyPotter
StatePA
Voltage115 kV
Capacity15 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2017-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy75
Mw Capacity15
Mfo75
Withdrawn Date2/22/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.