Substation Scout

Croydon 230kV

PJM queue ID T115 Terminal status

Queue IDT115
Project nameCroydon 230kV
Status (as published)Withdrawn
SubstationCroydon
Point of interconnectionCroydon 230kV
CountyBucks
StatePA
Voltage230 kV
Capacity32.5 MW
Resource (as published)Oil
Resource categoryOther (normalised for filtering)
Target commercial operation2010-05-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy32.5
Mw Capacity32.5
Mfo600
Withdrawn Date2/20/2008

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.