Substation Scout

North Temple 230kV

PJM queue ID S116 Terminal status

Queue IDS116
Project nameNorth Temple 230kV
Status (as published)Withdrawn
SubstationNorth Temple
Point of interconnectionNorth Temple 230kV
CountyBerks
StatePA
Voltage230 kV
Capacity912 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2011-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy912
Mw Capacity912
Mfo912
Withdrawn Date2/24/2009

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.