Substation Scout

Morrisville 500kV

PJM queue ID R77 Terminal status

Queue IDR77
Project nameMorrisville 500kV
Status (as published)Withdrawn
SubstationMorrisville
Point of interconnectionMorrisville 500kV
CountyWarren
StateVA
Voltage500 kV
Capacity600 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2012-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy600
Mw Capacity600
Mfo600
Withdrawn Date7/20/2009

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.