Queue IDR31
Project nameHopewell 230kV
Status (as published)Withdrawn
SubstationHopewell
Point of interconnectionHopewell 230kV
CountyCity of Hopewell
StateVA
Voltage230 kV
Capacity8 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2010-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy18
Mw Capacity8
Mfo18
Withdrawn Date4/27/2010