Substation Scout

City of Columbus

PJM queue ID Q30 Terminal status

Queue IDQ30
Project nameCity of Columbus
Status (as published)Withdrawn
SubstationCity of Columbus
Point of interconnectionCity of Columbus
CountyFranklin
StateOH
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Methane
Resource categoryGas (normalised for filtering)
Target commercial operation2006-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3
Mw Capacity0
Mfo3
Withdrawn Date9/20/2006

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.