Substation Scout

Walnut Ridge Wind Farm

PJM queue ID P20 Terminal status

Queue IDP20
Project nameWalnut Ridge Wind Farm
Status (as published)Withdrawn
SubstationNelson-Electric Junction
Point of interconnectionNelson-Electric Junction 345kV
CountyBureau
StateIL
Voltage345 kV
Capacity42 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2017-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy210
Mw Capacity42
Mfo210
Withdrawn Date12/14/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.