Substation Scout

Dixon-Mendota 34kV

PJM queue ID P17 Terminal status

Queue IDP17
Project nameDixon-Mendota 34kV
Status (as published)Withdrawn
SubstationDixon-Mendota
Point of interconnectionDixon-Mendota 34kV
CountyLee
StateIL
Voltage34 kV
Capacity4 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2006-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity4
Mfo20
Withdrawn Date2/2/2006

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.