Substation Scout

Ohio Central 138kV

PJM queue ID P02 Terminal status

Queue IDP02
Project nameOhio Central 138kV
Status (as published)Withdrawn
SubstationOhio Central
Point of interconnectionOhio Central 138kV
CountyMuskingum
StateOH
Voltage138 kV
Capacity550 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2007-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy550
Mw Capacity550
Mfo550
Withdrawn Date8/14/2006

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.