Rock Run Wind Park

PJM queue ID P01 Terminal status

Queue IDP01
Project nameRock Run Wind Park
Status (as published)Withdrawn
SubstationWestover-Madera
Point of interconnectionWestover-Madera 115kV
CountyCambria
StatePA
Voltage115 kV
Capacity13 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2011-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy65
Mw Capacity13
Mfo65
Withdrawn Date1/4/2013