Kanawha 138kV

PJM queue ID O57 Terminal status

Queue IDO57
Project nameKanawha 138kV
Status (as published)Withdrawn
SubstationKanawha
Point of interconnectionKanawha 138kV
CountyFayette
StateWV
Voltage138 kV
Capacity142 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2006-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy142
Mfo142
Withdrawn Date4/18/2006

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.