Gold Sabinsville

PJM queue ID N36 Terminal status

Queue IDN36
Project nameGold Sabinsville
Status (as published)Withdrawn
SubstationGold-Sabinsville
Point of interconnectionGold-Sabinsville 115kV
CountyPotter
StatePA
Voltage115 kV
Capacity10 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2014-12-15
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity10
Mfo50
Withdrawn Date1/15/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.