Substation Scout

Paw Paw 12 kV

PJM queue ID N19 Terminal status

Queue IDN19
Project namePaw Paw 12 kV
Status (as published)Withdrawn
SubstationPaw Paw
Point of interconnectionPaw Paw 12 kV
CountyLee
StateIL
Voltage12 kV
Capacity1.7 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2006-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.65
Mw Capacity1.65
Mfo1.65
Withdrawn Date9/6/2005

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.