Substation Scout

Clinton-Collier 345kV

PJM queue ID N18 Terminal status

Queue IDN18
Project nameClinton-Collier 345kV
Status (as published)Withdrawn
SubstationClinton-Collier
Point of interconnectionClinton-Collier 345kV
CountyAllegheny
StatePA
Voltage345 kV
Capacity19.2 MW
Resource (as published)Methane
Resource categoryGas (normalised for filtering)
Target commercial operation2005-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.2
Mw Capacity19.2
Mfo19.2
Withdrawn Date2/16/2005

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.