Substation Scout

Henry 138kV

PJM queue ID K24 Terminal status

Queue IDK24
Project nameHenry 138kV
Status (as published)Withdrawn
SubstationHenry
Point of interconnectionHenry 138kV
CountyGrant
StateWV
Voltage138 kV
Capacity30 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2005-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Capacity30
Mfo150
Withdrawn Date7/21/2004