Substation Scout

Freeport Wind Farm

PJM queue ID K04_CE19 Terminal status

Queue IDK04_CE19
Project nameFreeport Wind Farm
Status (as published)Withdrawn
SubstationFreeport Wind Farm
Point of interconnectionFreeport Wind Farm
CountyStephenson
StateIL
VoltageNot reported
Capacity16 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2011-10-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity16
Mfo80
Withdrawn Date9/26/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.