Substation Scout

Liberty Gap WF

PJM queue ID J07 Terminal status

Queue IDJ07
Project nameLiberty Gap WF
Status (as published)Withdrawn
SubstationNorth Franklin
Point of interconnectionNorth Franklin 138kV
CountyPendleton
StateWV
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2011-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy155
Mw Capacity0
Mfo155
Withdrawn Date6/28/2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.