PJM queue ID J01_MTX Terminal status

Queue IDJ01_MTX
Project nameHope Creek 500kV Cedar Creek 230kV
Status (as published)Withdrawn
SubstationHope Creek Cedar Creek
Point of interconnectionHope Creek 500kV Cedar Creek 230kV
CountyUnknown
StateDC
Voltage500 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mfo0
Withdrawn Date12/5/2003