Hinton 46kV

PJM queue ID I22 Terminal status

Queue IDI22
Project nameHinton 46kV
Status (as published)Withdrawn
SubstationHinton
Point of interconnectionHinton 46kV
CountySummers
StateWV
Voltage46 kV
Capacity41 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2004-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy41
Mw Capacity41
Mfo41
Withdrawn Date11/4/2003

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.