Forest 230kV

PJM queue ID H24 Terminal status

Queue IDH24
Project nameForest 230kV
Status (as published)Withdrawn
SubstationForest
Point of interconnectionForest 230kV
CountyElk
StatePA
Voltage230 kV
Capacity575 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2006-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy575
Mw Capacity575
Mfo575
Withdrawn Date11/13/2002