Brunner Island 230kV

PJM queue ID G33 Terminal status

Queue IDG33
Project nameBrunner Island 230kV
Status (as published)Withdrawn
SubstationBrunner Island
Point of interconnectionBrunner Island 230kV
CountyYork
StatePA
Voltage230 kV
Capacity1,200 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1200
Mw Capacity1200
Mfo1200

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.