Substation Scout

Homer City

PJM queue ID G09 Terminal status

Queue IDG09
Project nameHomer City
Status (as published)Withdrawn
SubstationHomer City
Point of interconnectionHomer City
CountyIndiana
StatePA
VoltageNot reported
Capacity547.5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2004-12-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy547
Mw Capacity547.5
Mfo547

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.