Substation Scout

Keystone

PJM queue ID F04 Terminal status

Queue IDF04
Project nameKeystone
Status (as published)Withdrawn
SubstationSomerset
Point of interconnectionSomerset 115kV
CountySomerset
StatePA
Voltage115 kV
Capacity30 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2005-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy30
Mfo30
Withdrawn Date4/14/2005

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.