Substation Scout

Burches Hill 500kV

PJM queue ID E22 Terminal status

Queue IDE22
Project nameBurches Hill 500kV
Status (as published)Withdrawn
SubstationBurches Hill
Point of interconnectionBurches Hill 500kV
CountyPrince William
StateVA
Voltage500 kV
Capacity960 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2005-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy960
Mw Capacity960
Mfo960
Withdrawn Date8/8/2002

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.