Substation Scout

Doubs 500 kV or 230 kV

PJM queue ID E05_W25 Terminal status

Queue IDE05_W25
Project nameDoubs 500 kV or 230 kV
Status (as published)Withdrawn
SubstationDoubs or
Point of interconnectionDoubs 500 kV or 230 kV
CountyFrederick
StateMD
Voltage500 kV
Capacity620 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2004-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy620
Mw Capacity620
Mfo620
Withdrawn Date11/26/2002

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.