Substation Scout

Passyunk 230kV

PJM queue ID D28 Terminal status

Queue IDD28
Project namePassyunk 230kV
Status (as published)Withdrawn
SubstationPassyunk
Point of interconnectionPassyunk 230kV
CountyPhiladelphia
StatePA
Voltage230 kV
Capacity550 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy550
Mw Capacity550
Mfo550
Withdrawn Date11/12/2002

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.