Substation Scout

Hay Road 69kV & 138kV

PJM queue ID D25 Terminal status

Queue IDD25
Project nameHay Road 69kV & 138kV
Status (as published)Withdrawn
SubstationHay Road &
Point of interconnectionHay Road 69kV & 138kV
CountyNew Castle
StateDE
Voltage69 kV
Capacity39 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy39
Mw Capacity39
Mfo39
Withdrawn Date9/17/2003

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.