Substation Scout

Stuart - Clinton 345 kV

PJM queue ID C01-2215 Terminal status

Queue IDC01-2215
Project nameStuart - Clinton 345 kV
Status (as published)Withdrawn
SubstationStuart - Clinton
Point of interconnectionStuart - Clinton 345 kV
CountyHighland
StateOH
Voltage345 kV
Capacity136.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-03-01
Source datasetcycle

Additional filed fields

DeveloperHighland Solar Transco Interconnection LLC
Transmission OwnerDAYTON
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy0.0
Mw Capacity136.6
Mfo400.0
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated6/9/2026