Roadstown 69 kV

PJM queue ID C01-2203 Terminal status

Queue IDC01-2203
Project nameRoadstown 69 kV
Status (as published)Withdrawn
SubstationRoadstown
Point of interconnectionRoadstown 69 kV
CountyCumberland
StateNJ
Voltage69 kV
Capacity105 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-06-01
Source datasetcycle

Additional filed fields

DeveloperCharged LLC
Transmission OwnerAEC
Project TypeGeneration Interconnection
CycleC01
StageApplication Review
Mw Energy104.9734
Mw Capacity104.9734
Mfo104.9734
Submitted Date4/27/2026
Withdrawn Date8/3/2026
Withdrawn RemarksCMN
Last Updated4/27/2026