Substation Scout

AXTON 765 kV

PJM queue ID C01-2110

Queue IDC01-2110
Project nameAXTON 765 kV
Status (as published)Active
SubstationAXTON
Point of interconnectionAXTON 765 kV
CountyPittsylvania
StateVA
Voltage765 kV
Capacity650 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2029-04-23
Source datasetcycle

Additional filed fields

DeveloperSTACK Danville Gen Power 2, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy650.0
Mw Capacity650.0
Mfo650.0
Submitted Date4/27/2026
Last Updated6/23/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.